Friday, April 23, 2021

Branson Creek Ph 2 - Flat Creek


Crew is moving equipment this morning to Fieldstone Liftstation to being transfer of sewage to Interceptor line. Electrician to be here to begin disconnecting power. 
8:35am- Electrician is onsite and Liberty is unhooking power to the station. 

9:05am- control panel is now removed from station. 

10:25am- flow is now being diverted into 12” line headed to Interceptor. 

12:10pm- lids are off and piping coming out now. 



1:04pm- last piece coming out. 

1:50pm-  safety fence is up and crew calling it a day. 







No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.