Crew will be working on Access 3 and Access 4 today.
7:54am- brush pile is lit on fire at MH E1 location to burn as they clear for Access 4.
9:03am- meeting with Chris to discuss converting Fieldstone Liftstaion over next week.
11:25am- met with Dale, contractor and Liberty at LS6 site about electrical. Thats all squared away now.
12:00pm- Dale will unhook power at Fieldstone on Monday per Flatcreeks request.
12:50pm- Access 4 getting opened up now.
3:11pm- back at fieldstone Liftstation and Dale has fixed the station. The #2 pump has been running none stop since noticed this morning. It was a float that was hung up apparently.
3:41pm- there us a manhole in the yard right where the new route for the forcemain goes from the clubhouse. I have contacted Tim with GRE about it since it looks live.
4:41pm- last strap on drop in MH A26 is now done.