Thursday, April 22, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on Access 3 and Access 4 today. 
7:54am- brush pile is lit on fire at MH E1 location to burn as they clear for Access 4. 

9:03am- meeting with Chris to discuss converting Fieldstone Liftstaion over next week. 

11:25am- met with Dale, contractor and Liberty at LS6 site about electrical. Thats all squared away now. 

12:00pm- Dale will unhook power at Fieldstone on Monday per Flatcreeks request.  

12:50pm- Access 4 getting opened up now. 



3:11pm- back at fieldstone Liftstation and Dale has fixed the station.  The #2 pump has been running none stop since noticed this morning. It was a float that was hung up apparently. 

3:41pm- there us a manhole in the yard right where the new route for the forcemain goes from the clubhouse. I have contacted Tim with GRE about it since it looks live. 

4:41pm- last strap on drop in MH A26 is now done. 










No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.