Wednesday, April 21, 2021

Branson Creek Ph 2 - Flat Creek


Crew melting snow from trailer bed so that a smooth drum roller can be hauled to Tom Heads for preparing roadway for paving. Access 3 will also get some attention today. 

11:30am- hill on Heads property is getting base rock added and leveled up. 

12:16pm- Access 3 is getting culverts i stalled and access 4 will be getting started on as well. 

4:38pm- access 4 off access 3 has been hit once so far more widening and cedar tree removal to occur tomorrow. 

Top of access 3 has also been straightened up as well. 

5:00pm- Heads hill has been based and rolled today. Now ready for paving.  












No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.