Monday, April 5, 2021

Branson Creek Ph 2 - Flat Creek


Crew to set meter vault today at LS6. 
7:23am- excavator will carry vault to LS6 site from top of hill at roadway. 

8:45am- crew has measured now and realized that the vault is built 11” to high. Nothing will be done here on this job now today. 



I will be checking on Ph 2 Interceptor job for rest of the day. 



No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.