Monday, May 17, 2021

Branson Creek Ph 2 - Flat Creek


Crew is onsite and awaiting rain to stop so they can work today. 
8:24am- crew will begin working on tie in of new 6” and old 6” from LS4. (Forcemain 4 @ STA 0+00) sheet 11A. 

9:35am- crew has now removed both bleed offs from lines that were tested and dug on out between the lines. 

10:49am- fittings are being tightened. 

11:13am- gravel going in on pipe and a partial bit of concrete was applied at fitting, but not acceptable due to to much water. Crew will concrete on another day as rain is beings again. This will round out the day here. 






No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.