Tuesday, May 18, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be concreting thrust blocks on 6” line at tie in from yesterday. LS 4 work with filter fabric and base rock to go down. 
8:15am- filter fabric onsite now at LS4. 

Spraying sterilant. 

Also at this time the thrust blocks are now poured on 6” tie in fittings from yesterday. 


11:53am- crew working to locate pressure line from pump at Pool house across from water tower. 



2:50pm- still putting down base rock over filter blanket here at LS4. 




No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.