Crew will be working on laying 2” pipe out to pump for club house today. They started it yesterday.
8:29am- more gravel going down at LS4.
9:50am- met with Junior w/ Boyce on getting 6” line tested at Fieldstone manhole now. BradW/ TCRSD has agreed to an air test and not a hydrostatic test. Boyce will get this scheduled.
11:33am- meter vault at LS4 has a leak at drain line that Chris will have to fix.
11:50am- crew working to get 2” pipe laid and are now out in Buffalo pin area.
5:00pm- 560’ of 2” was laid today headed out to club house manhole.