Wednesday, May 19, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on laying 2” pipe out to pump for club house today. They started it yesterday. 

8:29am- more gravel going down at LS4. 

9:50am- met with Junior w/ Boyce on getting 6” line tested at Fieldstone manhole now. BradW/ TCRSD has agreed to an air test and not a hydrostatic test. Boyce will get this scheduled. 

11:33am- meter vault at LS4 has a leak at drain line that Chris will have to fix. 

11:50am- crew working to get 2” pipe laid and are now out in Buffalo pin area. 

5:00pm- 560’ of 2” was laid today headed out to club house manhole. 







No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.