Wednesday, May 5, 2021

Branson Creek Ph 2 - Flat Creek


Crew will work on getting tie ins finished up today on 6” and 4” lines. 
7:06am- crew will finish breaking rock under water line and run lines to get tie ins done today. The 4” valve will be straightened up so a valve riser can be placed on it. 

11:25am- crew still working to get lines across intersection and getting the 4” tied in. Both old downstream 4” lines are now capped. 

3:40pm- 4” line in hooked up now to old 6” line. More 6” pipe to be laid for its tie in. 

Thrust blocks and encasement to be poured tomorrow. 





4:25pm- last of the fittings are being tightened. 

4:55pm- graveled up now and crew calling it a day. 









No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.