Crew will be working on getting top placed back on B line Liftstaion ( manhole) and getting that area cleaned up. Then thrust blocks will be poured at tie ins from yesterdays work.
12:30pm- pouring of thrust blocks begin.
12:57pm- more pouring of blocks.
Encasement pour-
1:20pm- all now completed.
4:13pm- crew will begin filling up the forcemains from LS 6 site today.
4:40pm- the 90* elbow at the second ARV from LS6 has a crack in it. Crew will stop filling and change out fitting now.