Tuesday, July 20, 2021

Branson Creek Ph 2 - Flat Creek


No work onsite this week other than start up at LS6 on Wednesday at 10:00am. 

Wednesday, July 7, 2021

Branson Creek Ph 2 - Flat Creek


No work onsite today- spoke with Boyce yesterday about manhole for clubhouse and Steve stated it would be a couple of weeks yet…

Friday, June 25, 2021

Branson Creek Ph 2 - Flat Creek


6:50am- crew should be back today to finish laying nase rock around station 6. 



Thursday, June 24, 2021

Branson Creek Ph 2 - Flat Creek


7:03am- work at LS6 today and Mandreling to be done on D line. 

7:13am- mandrel is pulled from wet well ar LS6 to MH D1 respectively. 






Wednesday, June 23, 2021

Branson Creek Ph 2 - Flat Creek


Paving to be done on Phase 1 at Mr. Heads property and LS6 to het more attention today. 
7:40am- Paving crew has arrived on Heads property. 



8:25am- 1st load of asphalt down.



8:53am- almost done with first lift on roadway. 

9:55am- to the top now. 96.97 tons laid so far. 

10:52am- almost finished with second pass. 

11:05am- lat truck! 175.01 tons used today. Property owner is extremely happy!














Monday, June 14, 2021

Wednesday, June 9, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be back at the cabin bench today. No work scheduled for Branson Creek. 

Tuesday, June 8, 2021

Monday, June 7, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be seeding and applying straw again today along with grading work at LS6. 
I will not be onsite today due to Interceptor work being delayed due to MH E26 not arriving until tomorrow. 

Friday, June 4, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be back spreading seed and straw in Pinnacle today. Also concrete to be poured at LS6 for pads. 
8:57am- rebar has been replaced in generator pad now. 

Also at this time Seed and straw is going down in Pinnacle. 

10:24am- more seeding and straw blowing. 

11:40am- I will be headed offsite for rest of the day. 


Thursday, June 3, 2021

Branson Creek Ph 2 - Flat Creek


6:55am- more cleanup today around storage yard and construction sites. 

3:00pm- Liftstaion 6 site is getting cleaned up now. 

Wrong size rebar will be removed and replaced with #5 before pour tomorrow on generator pad. 




Wednesday, June 2, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on more cleanup throughout the project. 

11:12am- more seed and straw going down at pool house tie in. 




Thursday, May 27, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be continuing cleanup and starting seeding and straw today on 2” line. 

11:29am- crew has seeded and now straw is getting placed across 2” line work. 



Crew was able to get both the 1-1/2” and the 2” lines tied in today before the rain respectively, left to right. 

1-1/2” line at toe of slope for pool house. 





Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.