No work onsite today.
Wednesday, June 30, 2021
Tuesday, June 29, 2021
Monday, June 28, 2021
Friday, June 25, 2021
Branson Creek Ph 2 - Flat Creek
6:50am- crew should be back today to finish laying nase rock around station 6.
Thursday, June 24, 2021
Branson Creek Ph 2 - Flat Creek
7:03am- work at LS6 today and Mandreling to be done on D line.
7:13am- mandrel is pulled from wet well ar LS6 to MH D1 respectively.
Wednesday, June 23, 2021
Branson Creek Ph 2 - Flat Creek
Paving to be done on Phase 1 at Mr. Heads property and LS6 to het more attention today.
7:40am- Paving crew has arrived on Heads property.
8:25am- 1st load of asphalt down.
8:53am- almost done with first lift on roadway.
9:55am- to the top now. 96.97 tons laid so far.
10:52am- almost finished with second pass.
11:05am- lat truck! 175.01 tons used today. Property owner is extremely happy!
Tuesday, June 22, 2021
Monday, June 21, 2021
Thursday, June 17, 2021
Wednesday, June 16, 2021
Tuesday, June 15, 2021
Monday, June 14, 2021
Thursday, June 10, 2021
Wednesday, June 9, 2021
Branson Creek Ph 2 - Flat Creek
Crew will be back at the cabin bench today. No work scheduled for Branson Creek.
Tuesday, June 8, 2021
Monday, June 7, 2021
Branson Creek Ph 2 - Flat Creek
Crew will be seeding and applying straw again today along with grading work at LS6.
I will not be onsite today due to Interceptor work being delayed due to MH E26 not arriving until tomorrow.
Friday, June 4, 2021
Branson Creek Ph 2 - Flat Creek
Crew will be back spreading seed and straw in Pinnacle today. Also concrete to be poured at LS6 for pads.
8:57am- rebar has been replaced in generator pad now.
Also at this time Seed and straw is going down in Pinnacle.
10:24am- more seeding and straw blowing.
11:40am- I will be headed offsite for rest of the day.
Thursday, June 3, 2021
Branson Creek Ph 2 - Flat Creek
6:55am- more cleanup today around storage yard and construction sites.
3:00pm- Liftstaion 6 site is getting cleaned up now.
Wrong size rebar will be removed and replaced with #5 before pour tomorrow on generator pad.
Wednesday, June 2, 2021
Branson Creek Ph 2 - Flat Creek
Crew will be working on more cleanup throughout the project.
11:12am- more seed and straw going down at pool house tie in.
Tuesday, June 1, 2021
Subscribe to:
Comments (Atom)
Branson Creek Ph 2 - Flat Creek
No work onsite this week other than start up at LS6 on Wednesday at 10:00am.
-
6:35am- crane is here and set up for placing of the wet well base today. 7:00am- crew says another foot or so of rock needs to be broke out...
-
7:05am- crew to begin laying force main today after truck is unloaded and tools get gathered. 7:35am- L.S. 1 will be excavated around for r...
-
7:03am- L.S.1 should be dug out enough, but will be shot for grade once bore crew arrives today. 7:32am- 1st joint of pipe for today now la...