Thursday, February 25, 2021

Branson Creek Ph 2 - Flat Creek


11:00am- casing is now placed and backfilling roadwY is underway. 

11:55am- roadway is now graveled and base rocked here at STA 49+00.  Roadway will now get opened back up. 

Jere a a few pictures of casing, pipe and rubber boots getting placed from earlier in the morning. 







1:53pm- dozer work now starting in Pinnacle for cleanup. 

3:17pm- more dozing occurs as dump truck hauls off spoil piles today here in Pinnacle. 



3:30pm- clearing for line B is happening now. 

4:05pm- I asked that roadways be swept today in Pinnacle and that the road crossing at STA 40+00 be graded down some so the “bump” would be eliminated. Crews have now completed these tasks. 








Wednesday, February 24, 2021

Branson Creek Ph 2 - Flat Creek


7:12am- crew is planning on doing roadway crossing today on 4” line at STA 16+00. 

7:56am- change of plans; now crew will cut roadway at 6” crossing at STA 40+00 and begin digging here today. 

8:55am- road crossing is now underway!

10:18am- slow progress. 

11:07am- a fitting is bolted up to head pipe on towards road cut. 

11:56am- more rock breaking occurring. 

1:47pm- half of roadway now has rock broken out. 

3:15pm- rock is almost broke all the way across roadway now. 

4:13pm- rock breaking now has to occur to get under electrical vault. 











Tuesday, February 23, 2021

Branson Creek Ph 2 - Flat Creek


Crew to work on encasement area at STA 2+50. 
7:25am- digging is started back now to expose area of encasement. 

8:50am- 2 joints of 4” now laid as crew digs closer towards encasement area. 

10:10am- tying up rebar for encasement. 

11:45am- ditch is dug and blocks placed as crew ties more rebar. 

1:10pm- cages going in around pipe now. Concrete to be onsite at 3pm today. 

2:24pm- my re cleanup today on 6” line. 

3:05pm- thrust blocks are getting poured on 6” line near road crossings and also on 4” line. 

4:15pm- encasement is now completed near STA 2+50. 

4:50pm- crew laid 7 joints today with encasement and thrust blocks poured. 











Monday, February 22, 2021

Branson Creek Ph 2 - Flat Creek


6:55am- Crew is working today. Jump starting tool truck now. 

7:43am- crew will work to expose more utilities near STA 16+00. 

9:14am- utilities are exposed as crew continues to look for fiber optic line.

10:45am- rock is now being broke around utilities. 

1:00pm- more rock is removed from around utilities. 

Also at this time crew will be working to get pipe closer to road crossings at STA 39+75 area. 

3:15pm- crew preparing to install pipe and 45* bends near STA 39+75 now that they have it dug out. 

3:50pm- bolting up fittings. 

4:10pm- street plates are now at STA 16+00 crossing for future use. Looks like some rock will need to be broke out in the roadway when the time comes to cross it. 











Friday, February 12, 2021

Branson Creek Ph 2 - Flat Creek


7:13am- More pipe to be laid. backfill and digging also continues today. 



9:48am- after a slow start due to the cold temps, crew is now setting air release structure at STA 5+07. 

11:06am- a 45* fitting will be placed to align with structure holes. 

12:04pm- pipe now passing through vault with 45* bend attached. 

1:20pm- crew jas now laid 5.5joints of pipe today so far. 

3:07pm- 15.5 joints now placed today. 

3:25pm- 16.5 joints now placed as this will be all that is laid here today due to a sewer line crossing that will need to be done. Excavator will backfill this area and cleanup some. 

4:15pm- backfill now almost complete for the day. 











Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.