11:00am- casing is now placed and backfilling roadwY is underway.
11:55am- roadway is now graveled and base rocked here at STA 49+00. Roadway will now get opened back up.
Jere a a few pictures of casing, pipe and rubber boots getting placed from earlier in the morning.
1:53pm- dozer work now starting in Pinnacle for cleanup.
3:17pm- more dozing occurs as dump truck hauls off spoil piles today here in Pinnacle.
3:30pm- clearing for line B is happening now.
4:05pm- I asked that roadways be swept today in Pinnacle and that the road crossing at STA 40+00 be graded down some so the “bump” would be eliminated. Crews have now completed these tasks.