Friday, April 30, 2021

Branson Creek Ph 2 - Flat Creek


Crew will reset riser section on LS6 today then put risers on LS 4 at maintenance shed. 
12:28pm-  Rack is up for electrical and new barrel section is on wet well at LS 6. 

12:32pm- new barrel sections are also on LS 4 at Maintenance Shed. 

I will now be headed offsite. No more work to be done today. 


Thursday, April 29, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working to clean, pump and then concrete new flowline at B line Liftstaion. 
8:10am- Boremans now here pumping station out. 

Crew power washing. 

8:44am- bypass in place and gravel going in now. 

9:22am- rebar reinforcement is now placed.

10:49am- concrete work begins. 

11:53am- concrete work is completed. 








Tuesday, April 27, 2021

Branson Creek Ph 2 - Flat Creek


Crew will work on B line Liftstaion today dismantling it and pulling mandrel on B line. 
11:01am- crew preparing to pull mandrel on B line 

11:17am- mandrel now pulled from existing manhole to B1. 

11:28am- mandrel now pulled from B1 to B2. 

11:42am- Mandrel now pulled from B2 to L.S.  

5:14pm- B line Liftstaion is offline now and flow will be headed to Fieldstone manhole. 

Fieldstone manhole has 6” forcemain entering it now. A drop will be installed on it yet this week sometime. 











Monday, April 26, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on Fieldstone Liftstaion today to finish converting it to a manhole. 
8:12am- crew awaiting Boremans to pump out wet well before by-pass is installed. 

9:17am- washing down station now with Boremans pumping. 

9:38am- gravel going in now. 

9:50am- Jimmy will grade out gravel now. 

10:21am- rebar reinforcement is now placed. 

12:15pm- flowline is now poured. 



5:20pm- forcemain is cur and headed to manhole now. Coring to take place tomorrow. Live flow now going across flowline. 











Friday, April 23, 2021

Branson Creek Ph 2 - Flat Creek


Crew is moving equipment this morning to Fieldstone Liftstation to being transfer of sewage to Interceptor line. Electrician to be here to begin disconnecting power. 
8:35am- Electrician is onsite and Liberty is unhooking power to the station. 

9:05am- control panel is now removed from station. 

10:25am- flow is now being diverted into 12” line headed to Interceptor. 

12:10pm- lids are off and piping coming out now. 



1:04pm- last piece coming out. 

1:50pm-  safety fence is up and crew calling it a day. 







Thursday, April 22, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on Access 3 and Access 4 today. 
7:54am- brush pile is lit on fire at MH E1 location to burn as they clear for Access 4. 

9:03am- meeting with Chris to discuss converting Fieldstone Liftstaion over next week. 

11:25am- met with Dale, contractor and Liberty at LS6 site about electrical. Thats all squared away now. 

12:00pm- Dale will unhook power at Fieldstone on Monday per Flatcreeks request.  

12:50pm- Access 4 getting opened up now. 



3:11pm- back at fieldstone Liftstation and Dale has fixed the station.  The #2 pump has been running none stop since noticed this morning. It was a float that was hung up apparently. 

3:41pm- there us a manhole in the yard right where the new route for the forcemain goes from the clubhouse. I have contacted Tim with GRE about it since it looks live. 

4:41pm- last strap on drop in MH A26 is now done. 










Wednesday, April 21, 2021

Branson Creek Ph 2 - Flat Creek


Crew melting snow from trailer bed so that a smooth drum roller can be hauled to Tom Heads for preparing roadway for paving. Access 3 will also get some attention today. 

11:30am- hill on Heads property is getting base rock added and leveled up. 

12:16pm- Access 3 is getting culverts i stalled and access 4 will be getting started on as well. 

4:38pm- access 4 off access 3 has been hit once so far more widening and cedar tree removal to occur tomorrow. 

Top of access 3 has also been straightened up as well. 

5:00pm- Heads hill has been based and rolled today. Now ready for paving.  












Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.